5GDHC network in Dollnstein
On this page you find facts and figures about the 5GDHC network in Dollnstein (Dollnstein). The network has a length of 1.8 km. In total, 35 buildings are supplied by the heat network. The 5GDHC network is operated by Kommunalunternehmen Dollnstein .
Facts and figures about the cold heat network in Dollnstein (Dollnstein)
Insulated steel pipes are used for the heating network. In this district, unlike in other districts, the 5GDHC network is only used to provide heat. A cooling supply is not considered. The share of new construction area in this district is 0 %. Every building of the district is free to decide whether to connect to the heating network or not; there is no obligation to connect. Detailed data of the 5GDHC network in Dollnstein (Dollnstein) is listed in Table 1.
District | Dollnstein |
Country | Germany |
City / location | Dollnstein |
Year of commissioning | 2014 |
Operator | Kommunalunternehmen Dollnstein |
Network temperatures | W: 65-75, S: 20-35 °C |
Supplied buildings | 35 |
Network length | 1.8 km |
Share of new building area | 0 % |
Heat generation capacity (energy hub) | 980 kW |
Pipe type | Steel pipe (insulated) |
Heat sources |
Solar thermal collectors Combined heat and power plant (CHP) Boiler (e.g. natural gas/biogas) Ground water / wells |
Cooling supply through thermal network | No |
Obligation to connect to network | No |
Owner of decentral heat pumps | Heat network operator |
Billing boundary for delivered heat | Condenser of the heat pump (building side) |
Price model for heat supply |
Base price (€/year) Energy price (€/kWh) Capacity price (€/kW) |
Buildings receiving compensation for heat feed-in | No |
This might also interest you
nPro software
Plan your energy system with nPro!